Artwork for the roundabout centerpiece is beginning to take shape in artist Elijah Burnett’s shop. Courtesy Photos

Artwork for the roundabout centerpiece is beginning to take shape in artist Elijah Burnett’s shop. Courtesy Photos

Johnson Parkway Roundabout full speed ahead

The Johnson Parkway-Highway 305 roundabout project is coming along as Poulsbo hears an update from the city’s Engineering Department.

“The teams been working very well and very hard to keep this project moving and also to work in this new arrangement with WSDOT doesn’t usually do with smaller projects, and it’s working out really well,” said Diane Lenius, director of city Engineering.

Construction began in January and is expected to be completed in late January or early February of 2022. The project encompasses not only the roundabout but also a shared-use path and pedestrian tunnel, and mitigation efforts to address infrastructure, stormwater, and impacts on local waterways.

The project also includes art at the roundabout that reflects Poulsbo and its neighbors in Suquamish.

“To date what we have done so far is installed the culverts for two streams. We just started the culvert installation for Bjorgen Creek and anticipate to be setting footings next week,” said Josh Ranes, city civil engineer. “You may have seen already we got rid of the bypass road that came through the roundabout site and have paved the road through Lemolo and have got traffic back on the road to the main alignment of the roundabout.”

There’s also been installation of curbs, sidewalks and paving on the south side of the roundabout. The pedestrian tunnel is about 70 percent complete. Finally, about 1,400 feet of the joint utility trench has been installed.

“The joint utility trench is an effort to combine multiple utilities into one trench in planning for future use,” Ranes said.

The trench will allow for groups like Puget Sound Energy, Comcast, Centurylink, Kitsap Public Utility District, city of Poulsbo and Cascade Natural Gas to have access to key lines as more development happens.

The project was budgeted at $18.8 million, with a contract bid for $15.3 million. Of that, $6.4 million has been paid, and there have been $37,520 in change orders thus far, though Ranes expects there will be more.

“This is a very large project and with that expect some surprises along the way. We have already received some surprises but where we are in the project to be at this level of change orders is really great. We have a few change orders that are going to be a bit larger than we are working on now that we’re working through negotiations with the contractor currently,” Ranes said.

Ranes and the Engineering Department had the opportunity to visit with artist/blacksmith Elijah Burnett, who is working on the art centerpiece for the roundabout. Burnett’s design of a forged metal sculpture that ties together the environmental, Nordic and Native heritage of Poulsbo was a topic of great discussion back in January.

“We got to go out and take a look at his shop and see his progress and actually watch him in action and see how he’s starting to mold some of these pieces… it was a really fun thing to go out and see,” Ranes said.

One side of the pedestrian tunnel.

One side of the pedestrian tunnel.

One of the three culverts that has been formed as part of the roundabout project.

One of the three culverts that has been formed as part of the roundabout project.

A birds-eye view of the roundabout shows some of the progress that has been made on the Johnson project.

A birds-eye view of the roundabout shows some of the progress that has been made on the Johnson project.

A joint untility trench has been created for easy access for multiple infrastructure agencies along the Johnson roundabout project. .

A joint untility trench has been created for easy access for multiple infrastructure agencies along the Johnson roundabout project. .

Crews work to form the curbing of the roundabout.

Crews work to form the curbing of the roundabout.

Beautifully paved road down to Lemolo Shore Drive.

Beautifully paved road down to Lemolo Shore Drive.

More in News

.
Kitsap span included in $605 million fix for state bridges

Port Washington bridge on SR 303 is part of infrastructure package

.
USS Kitty Hawk bids farewell

Iconic aircraft carrier towed through Rich Passage into the mists of history

Nine local “Healthcare Heroes” were recently recognized by the Poulsbo City Council for their various efforts during the COVID pandemic. Courtesy photo
Local ‘Healthcare Heroes’ recognized by Poulsbo council

It also approves $10k of ARPA funding for COVID tests for small businesses

.
South Kitsap schools announce emergency closure Jan. 14-18

District officials say there’s not enough staff to conduct classroom learning

Neon lights and signs gives My Girl a 1950s feel, along with all the other collectibles from that time period.
Talkin’ ‘bout My Girl: Drive-In & Museum in Kingston

Where in Kingston can one find a movie trailer once used by… Continue reading

.
Transportation top city’s 2022 needs list

Mayor Putaansuu outlines Port Orchard’s upcoming projects — and how to pay for them

.
NKSD ready if there’s a COVID outbreak

Last week parents and schools received two pieces of good news: the… Continue reading

.
COVID rates going up for young people

The Department of Health has tracked cases among children statewide, along with… Continue reading

.
1,972 new COVID cases confirmed in Kitsap over holiday weekend

Over the last week, Kitsap’s case rate per 100,000 residents has skyrocketed to 1,340.6

Most Read