Noll Road construction resumes in Poulsbo

Construction on the Noll Road north segment has resumed after a break due to the holidays and inclement weather, per a city of Poulsbo newsletter.

Grading and installation of driveways, sidewalks, and roadway, and paving of the shared use path will be ongoing through February, weather dependent. Streetlights, signs, and lighting are all being installed along the project route, the newsletter says. The new roundabout at the intersection of Noll Road, Mesford Road, and Langaunet Lane is the next focus, with curbs being installed and the new storm drain system going in. Completion is expected in late spring or early summer.

The next phase of this project will be the middle segment, with design plans now advancing to 60% completion. This phase includes the section between Hostmark Street and the new roundabout being constructed at Noll Road and Mesford Road. An open house for the middle segment design is scheduled to take place Feb. 25 at 5 p.m. at City Hall, to provide an overview of the upcoming work and allow time for questions regarding the project, per the newsletter.